Our Products
Compressed Air Solutions
  • Screw Air Compressor
  • Oil Free Compressor
  • Diesel Portable Compressor
  • Gas Compressor
  • Specialty Compressor
  • Air Treatment
ISO 9001 Certified
24-Month Warranty
OEM & ODM Support
Factory Direct Price
All products→
Planning a Compressed Air System
System Design

Planning a Compressed Air System

Technical Guide
22 min read

Planning a compressed air system is calculating a ten-year bill.

Many people planning compressed air systems focus all attention on equipment purchasing. This machine costs how much, that machine costs how much, comparing quotes back and forth. This thinking is wrong from the start.

Compressed air system cost structure is different from most industrial equipment. Equipment purchasing only accounts for two to three tenths of total ownership cost. Remaining seven tenths or more is electricity.

Buy a compressor, run it ten years, money paid to the power company is several times the cost of buying the machine.

Specific power, this parameter, many people don't pay much attention. Figure a difference of a few tenths doesn't matter. Do the math and you'll know if it matters: specific power difference of 0.5 kW/(m³/min), for a 350 CFM machine, means 5 more kWh every hour. Run 8,000 hours a year, that's 40,000 kWh a year. Industrial electricity at seven cents, $2,800 more per year. Ten years is $28,000. Saved $5,000 at purchase buying a machine with higher specific power, ten years you're out twenty-plus thousand.

Many people don't do this math, or do it and don't take it seriously. Equipment purchasing goes through capital expenditure, electricity goes through operating cost. Two pots of money come from different pockets. Decision makers might not even be the same people. Purchasing department completed their task. Electricity cost is production department's problem. By the time production department notices electricity cost is sky high, equipment's already been bought.

So planning phase must get this math done clearly, and make sure decision makers see this math.

Industrial compressor system
Electricity is the big cost. Typically 70 percent or more of total ownership

VFD

These years VFD compressors are hot. Manufacturers advertise 30%, 40% energy savings, sounds tempting. Many people hear energy savings and go VFD, regardless if their conditions are suitable.

VFD machines save electricity by adjusting speed based on air demand. High demand, high speed. Low demand, low speed. Avoids fixed-speed machine's load/unload cycling. Fixed-speed machine unloading doesn't produce air, but motor still spinning, wasting electricity. VFD machines save this waste.

Problem is, VFD itself has losses from the inverter, and electrical requirements for installation are more involved than a fixed-speed machine. Full load operation, efficiency actually slightly lower than fixed-speed. Stable load conditions, fixed-speed running full load, efficiency highest. High load fluctuation conditions, VFD advantage shows.

What counts as high load fluctuation? Morning shift air demand twice the night shift, that's high fluctuation. Morning full load afternoon only half, that's high fluctuation. Air demand throughout the day changes less than 20%, that's stable. Going VFD won't save much money.

How to know if your plant has high load fluctuation? Measure. Clamp a current recorder on existing compressor power wires. Collect one week or even one month of data. Current curve shape tells everything: curve flat like a straight line, fixed-speed is enough. Curve jumping up and down, VFD can save money.

New projects without historical data can look at quality requirements by industry and similar process load profiles as a starting reference. Really can't find a reference, rent equipment first and run a few months to get baseline. Better than guessing. Select equipment wrong.

Multi-unit systems have one configuration worth considering: one VFD plus several fixed-speed. VFD specifically handles load fluctuation, speed follows air demand. Fixed-speed either runs full load or stops, always working at optimal efficiency point. System pressure stabilized by VFD, fixed-speed doesn't participate in pressure regulation. This configuration brings out advantages of both machine types.

• • •

Sequencing

Multiple compressors must have sequencing control. Can't emphasize this enough.

Compressor control system
Compressor control system

System without sequencing control, what's that like? Each machine has its own pressure switch. Pressure below lower limit, load. Above upper limit, unload. Three machines each minding their own business. System pressure dips slightly, all three load together. Pressure spikes slightly, all three unload together. Pressure curve swinging wildly. Load/unload count hits hundreds per day. High electricity, short equipment life, pressure still unstable. A properly sized receiver tank provides buffer volume.

Installing a sequencing controller costs how much? Few thousand dollars. Annual electricity savings? Maybe several times that amount. Several machines coordinating together. How many should run, run how many. Each one's loading level, orderly. System pressure stable, load/unload count greatly reduced.

Some plants to save that few thousand dollars on controller, annual extra electricity cost is far more than that amount.

Pressure

Air-using equipment in the plant won't all have same pressure requirement. (asme compressor performance test ) Most equipment 85 psi is enough. A few need 115 psi or even 145 psi. Easiest approach is configure to highest requirement, whole plant at 145 psi. Cost of this decision: all equipment, all the time, using pressure 60 psi higher than actually needed. Compressor to produce this extra 60 psi, uses nearly 30% more electricity. A few high pressure pieces of equipment, making whole plant pay for them.

Correct approach is configure main system at 85 psi. Boosters raise 85 psi to 145 psi locally, and OSHA pressure vessel compliance stays contained to that one skid instead of applying to the entire plant piping network. Booster equipment investment plus operating power consumption, way less than raising whole system pressure.

Pipe pressure drop must be factored in too. Compressor station outlet 100 psi, pipe runs long, many elbows, pipe diameter too small, by the time it gets to workshop end might only be 80 psi. Planning phase estimate this loss, don't wait until system is built to find end pressure isn't enough.

Compressor room design checklist sets layout pipe routes and exhaust paths.

Industrial air system
Industrial air system

Sizing

Air demand calculation is starting point for all calculations. Adding up nameplate consumption then multiplying by simultaneous use factor is standard practice. Factor usually 0.6 to 0.8. Measured load curve more reliable, especially for retrofit projects. Historical data right there, waste not to use it.

Reserve margin depends on company's own growth plans. No standard percentage. Aggressive expansion, leave more. Steady progress, leave less. Leave too much, equipment runs inefficiently long-term. Leave too little, production expansion gets bottlenecked.

Post-treatment equipment, enough is enough. Paint spray sensitive to oil. A compressed air system for manufacturing electronics is sensitive to particles. Ordinary pneumatic tools not that picky. Distinguish applications follow different compressed air quality standards . What should be high, high. What can be low, low. Don't configure whole plant to highest standard "for insurance." Desiccant dryer regeneration eats 10% to 15% of compressed air. Configure too much and that's waste.

Compressed air demand calculation totals every tool and adds 25 percent margin.

Machine room ventilation must be good. Compressors generate lots of heat. Inlet should avoid pollution sources. Leave space for future equipment additions. Pipe network run loop if possible, end pressure more even, also has redundancy. An installation checklist covering ventilation, inlet placement, loop piping, and expansion space catches most of these before commissioning.

Compressor installation checklist walks through anchor bolts wiring and piping startup.

Equipment configuration, big and small mixed or uniform spec, depends on load curve shape. Base load proportion high, configure more big machines. Fluctuation severe, increase small machine proportion. Exactly how to configure has no formula. Must look at measured data.

Footer Component - SOLLANT
滚动至顶部